• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

California NFPA 25 Flushing of Connection to Riser

I can logically assume that since a deluge valve is below the open head piping system, they require the pipe below the valve and underground supply flushed. This is not unusual since all underground water supply to a riser needs to be flushed in accordance with the table in NFPA 13 for water supply.
 
Found out they only require open the main drain and flow water.


Just poorly written and no explanation of what is actually required.
 