• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

drain down time

  1. S

    Flow control roof drains allowed to install with declaration where the maximum drain down time exceeds 24 h

    This is from Ontario building code Division B part 7: ----------------------------------------------------------------------------------------------------------------------------------- 7.4.10.4. Hydraulic Loads from Roofs or Paved Surfaces ... (2) Flow control roof drains may be installed...