Scenario: concrete footer poured for single story room addition. Concrete dries overnight, but footer determined to be too shallow. Holes are drilled into dry concrete, filled with epoxy and additional rebar is inserted, a layer of a bonding substance is spread over top of dry concrete footer before additional 2 to 4 inches of wet concrete is poured on top in order to raise height of footer. Is the footer sound constructed in this way, will this meet code, will the inspector be able to tell two layers were poured?