R401.3 Drainage.
Surface drainage shall be diverted to a storm sewer conveyance or other approved point of collection that does not create a hazard. Lots shall be graded to drain surface water away from foundation walls. The grade shall fall not fewer than 6 inches (152 mm) within the first 10 feet (3048 mm).
Exception: Where lot lines, walls, slopes or other physical barriers prohibit 6 inches (152 mm) of fall within 10 feet (3048 mm), drains or swales shall be constructed to ensure drainage away from the structure. Impervious surfaces within 10 feet (3048 mm) of the building foundation shall be sloped not less than 2 percent away from the building.
************************************
We believe our concrete patio wasn’t built to code. I have posted the IRC 2015 code for drainage above, as this is the code the city, we live in has adopted. We believe the 2% slope requirement applies to covered or uncovered concrete patios because the code doesn’t exempt covered patios. Our General Contractor doesn’t believe it applies. Our local code inspector doesn’t either, but it is a small city, so they don’t inspect slabs/patios, so I don’t think he is really informed. I have contacted a couple of larger municipalities near us and they have both told me it doesn’t matter if the impervious surface is covered or not covered the slope requirements in R401.3 apply to both.
Are we correctly interpreting the code that it should have been poured with a 2% and not level in the first 10'? Where can I find information to back up that R401.3 wasn’t met? I need something more than my opinion and the opinion of a couple of local code inspectors to convince my GC this is something that needs to be fixed.
************************************
It isn't letting me attach a picture. Here is a little background on the patio.
The concrete patio area is 20’ x 15’ with two sides against the house. There is a sliding door on the 20’ section and a single door on the 15’ section. We asked for a walk-out patio and not a step-down. The GC’s subcontractor unfortunately didn’t slope it much, so it doesn’t drain well. They sloped it a total of 1.5” over a span of 25’ - from the corner where the wall of the addition meets the existing house to the far corner of the patio. However, the 1.5” slope doesn’t really start to slope until the middle of the patio. Therefore, the patio is level near the house. In fact, the first 10’ of the patio from the addition wall and also the existing house is flat and level. Some areas of the patio are level for 20’. It is basically flat enough that you could easily build on it.
The concrete is mostly covered but there are a few feet that aren’t covered. Since it was poured a month ago, we have only had light showers and already water puddles and slowly back-ups toward the middle of the patio because it is too flat for it to drain off. It then takes hours for the water to evaporate off the patio even though we live where it is 100+ in the summer. We live where we get thunderstorms where water blows, so I foresee water blowing in under the covered area. Not draining is concerning to us, especially because we asked for a walk-out patio, making it much easier for water to back up into the house without the proper slope. We also get freezing rain and freezing temperatures in the winter which could result in the patio becoming an ice skating rink.
Making things even more complicated is the patio had 3 columns that support the roof, so replacing the patio is going to be a huge challenge.
Surface drainage shall be diverted to a storm sewer conveyance or other approved point of collection that does not create a hazard. Lots shall be graded to drain surface water away from foundation walls. The grade shall fall not fewer than 6 inches (152 mm) within the first 10 feet (3048 mm).
Exception: Where lot lines, walls, slopes or other physical barriers prohibit 6 inches (152 mm) of fall within 10 feet (3048 mm), drains or swales shall be constructed to ensure drainage away from the structure. Impervious surfaces within 10 feet (3048 mm) of the building foundation shall be sloped not less than 2 percent away from the building.
************************************
We believe our concrete patio wasn’t built to code. I have posted the IRC 2015 code for drainage above, as this is the code the city, we live in has adopted. We believe the 2% slope requirement applies to covered or uncovered concrete patios because the code doesn’t exempt covered patios. Our General Contractor doesn’t believe it applies. Our local code inspector doesn’t either, but it is a small city, so they don’t inspect slabs/patios, so I don’t think he is really informed. I have contacted a couple of larger municipalities near us and they have both told me it doesn’t matter if the impervious surface is covered or not covered the slope requirements in R401.3 apply to both.
Are we correctly interpreting the code that it should have been poured with a 2% and not level in the first 10'? Where can I find information to back up that R401.3 wasn’t met? I need something more than my opinion and the opinion of a couple of local code inspectors to convince my GC this is something that needs to be fixed.
************************************
It isn't letting me attach a picture. Here is a little background on the patio.
The concrete patio area is 20’ x 15’ with two sides against the house. There is a sliding door on the 20’ section and a single door on the 15’ section. We asked for a walk-out patio and not a step-down. The GC’s subcontractor unfortunately didn’t slope it much, so it doesn’t drain well. They sloped it a total of 1.5” over a span of 25’ - from the corner where the wall of the addition meets the existing house to the far corner of the patio. However, the 1.5” slope doesn’t really start to slope until the middle of the patio. Therefore, the patio is level near the house. In fact, the first 10’ of the patio from the addition wall and also the existing house is flat and level. Some areas of the patio are level for 20’. It is basically flat enough that you could easily build on it.
The concrete is mostly covered but there are a few feet that aren’t covered. Since it was poured a month ago, we have only had light showers and already water puddles and slowly back-ups toward the middle of the patio because it is too flat for it to drain off. It then takes hours for the water to evaporate off the patio even though we live where it is 100+ in the summer. We live where we get thunderstorms where water blows, so I foresee water blowing in under the covered area. Not draining is concerning to us, especially because we asked for a walk-out patio, making it much easier for water to back up into the house without the proper slope. We also get freezing rain and freezing temperatures in the winter which could result in the patio becoming an ice skating rink.
Making things even more complicated is the patio had 3 columns that support the roof, so replacing the patio is going to be a huge challenge.