Working on a new building with 2018 IBC.
Basement parking with ground floor apartments in a Type 1A structure under Floors 2-5 apartments - construction type to be determined:
510.2 Horizontal Building Separation allows 4 more floors of Type 5A construction above the 3 hour assembly on top of the 1A structure.
510.4 seems to add the restriction that the max number of floors above the Type 1A construction begins counting not at the 3 hour horizontal assembly, but at the level of the floor above the parking.
This seems clear until you look at the commentary for 510.2 which uses a Group R over Parking example but seems to contradict the requirements of 510.4 and states that you start measuring from the horizontal separation.
I don't have commentary for 510.4 so I can't see if that commentary contradicts the 510.2 commentary. I also might be reading Section 510.4 incorrectly.
Basement parking with ground floor apartments in a Type 1A structure under Floors 2-5 apartments - construction type to be determined:
510.2 Horizontal Building Separation allows 4 more floors of Type 5A construction above the 3 hour assembly on top of the 1A structure.
510.4 seems to add the restriction that the max number of floors above the Type 1A construction begins counting not at the 3 hour horizontal assembly, but at the level of the floor above the parking.
This seems clear until you look at the commentary for 510.2 which uses a Group R over Parking example but seems to contradict the requirements of 510.4 and states that you start measuring from the horizontal separation.
I don't have commentary for 510.4 so I can't see if that commentary contradicts the 510.2 commentary. I also might be reading Section 510.4 incorrectly.