Hello,
Hoping someone can help shed some light on how this table is used. I have designs underway for a mixed use 12,000 sf 2 story building....F1 use (catering kitchen) and S on first floor, B use on second floor. Designs are coming along. Jury is still out on the classification being either 5A or 3B. I'm weighing the options with that.
Clients just threw me a monkey wrench by wanting to shift the new building over to connect with another existing building on the site. Buildings will touch but no proposed connection (doorway) at this time, perhaps in the future.
Here's my question, does Table 705.8 column "Fire Separation Distance" specifically pertain to the proximity of my new building to the existing building?
I can't see how that would be since any FSD of 0-3 feet doesn't permit any openings at all, which seems very unrealistic, so I must be missing something here.
Appreciate any insight. Thanks.
Hoping someone can help shed some light on how this table is used. I have designs underway for a mixed use 12,000 sf 2 story building....F1 use (catering kitchen) and S on first floor, B use on second floor. Designs are coming along. Jury is still out on the classification being either 5A or 3B. I'm weighing the options with that.
Clients just threw me a monkey wrench by wanting to shift the new building over to connect with another existing building on the site. Buildings will touch but no proposed connection (doorway) at this time, perhaps in the future.
Here's my question, does Table 705.8 column "Fire Separation Distance" specifically pertain to the proximity of my new building to the existing building?
I can't see how that would be since any FSD of 0-3 feet doesn't permit any openings at all, which seems very unrealistic, so I must be missing something here.
Appreciate any insight. Thanks.