• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

Peeved over the permit process

mark handler

SAWHORSE
Joined
Oct 25, 2009
Messages
11,677
Location
So. CA
Peeved over the permit process
City says repairs were started before permit issues
http://www.ptleader.com/news/peeved...cle_7617060c-270e-11e8-86fc-2bf7c6381cf3.html
upload_2018-3-14_5-50-59.png
A contractor hired to repair a fire-damaged Port Townsend home is protesting what he says are excessive city permit fees and delays in issuing permits for the project by placing large plywood signs in the front yard.
“It took the city 6 weeks for a repair permit. Then they charged $1,816.44,” one of several signs at 535 Harrison St. declared.
Michael McCutcheon, who is doing the repair work with Olympic Steel on behalf of the owner, said the City of Port Townsend initially estimated it would cost $900-$1,200 for a permit for the work.
“That’s pretty standard,” he said of the estimate. However, the final cost of the repair permit was $1,816.44, which McCutcheon felt was excessive. The permit, which was posted outside the home, showed not just one but two entries for “plan review fees” at $352 each, as well as two entries for “building permit fees” at $542 each.
“He just doubled everything,” McCutcheon said of the city employee who doubled the fees.
CITY RESPONSE
Lance Bailey, director of Development Services for the city, said the higher fees were a result of McCutcheon doing some initial work without a permit, and that the city filed a “stop work” order as a result of that work.
City building inspector Dennis Perkon posted the “stop work” order on the home on Jan. 31 after seeing that roof trusses and other repair materials had been placed on the home.
McCutcheon countered that the initial work was basic cleanup and board-up work. The preparatory work was similar to the sort of basic work a cleanup company like Servpro might do, McCutcheon said, adding that the city did not require Servpro to get permits for that sort of work.
Bailey said that if the only work being done at the home was related to cleaning up, then no permit was needed. But if the work involved demolition or changing the structure of the property, a permit was needed, he said.
McCutcheon said he went ahead and paid the $1,816.44 fee “just to keep going forward. It was a ripoff. And what it does is it raises the price of all our insurance,” he said.
“It’s just wrong that one person in the city makes the decision that he’s going to charge double the fees,” McCutcheon said.
McCutcheon also said it took too long – six weeks – for the city to finally grant the permit.
A clerk with the city’s Development Services department said the request for a permit was originally filed Jan. 11, which means it took the city six weeks and four days to issue the permit, on Feb. 27. The department received a request to expedite the permit on Feb. 6 so that the tenant who was displaced by the fire would be able to return to his home sooner.
“I think people really need to know what’s going on … the neighbors need to know why it took so long to get a permit because it will happen to somebody out there again,” McCutcheon said.
“I don’t believe that any organization should have the right to control anybody like that,” he said.
DECEMBER FIRE
McCutcheon was doing the work to repair damage caused by a fire that broke out in the home on Dec. 12, 2017.
Bill Beezley, public information officer for East Jefferson Fire Rescue (EJFR), said firefighters were dispatched to the fire at 9:31 p.m. The home is one block away from the Uptown fire station. Firefighters arrived at 9:33 p.m., Beezley said.
McCutcheon said the fire department did a good job in limiting smoke damage to the house. He said firefighters cut a hole in the roof to vent the smoke.
“The place was in pretty good shape,” he said.
The fire displaced a tenant in his 70s who had failing health, McCutcheon said.
McCutcheon said he thought the Red Cross provided housing for the man immediately after the fire, and that the tenant had since moved into an assisted living home.
EJFR fire investigator Wayne Kier wrote that the probable cause of the fire was that someone had placed an incandescent bulb of the incorrect size into a ceiling light fixture in the kitchen. The light fixture overheated, causing insulation in the attic to catch on fire, Kier wrote.
Repairs to the house are to include new asphalt roofing material, seven new roof trusses, new cabinets, a new kitchen floor, a new bathtub, a new floor in the bathroom, new carpeting and more.
According to city documents, Olympic Steel LLC is to be the primary contractor for the work, and the valuation of the repair is $40,000.
According to Jefferson County Assessor records, the property has a value of $276,976.
The home should be repaired by April 1, McCutcheon said. The home is owned by Amell Family Limited Partnership, which has an address in Concord, California.
WITHOUT PERMIT
Bailey said it was apparent that there was “work going on in the absence of a permit,” and that the work at 535 Harrison St. was “over and beyond just cleanup.”
Bailey said that trusses leaning against the building and materials placed on the roof “reasonably” led the building inspector to believe work was being done at the property.
Complicating matters was that the city was not sure about the legality of how the home had been subdivided into multiple rental units including a “535 B” address, Bailey said. Resolving that question took time before the city could issue the permit. The city eventually determined the subdivision was acceptable.
Bailey said public safety was one of the city’s main concerns when it came to the permits. He noted that in the three years he’s worked for the city, there had been a number of house fires.
“There seems to be an uptick” in home fires, Bailey said, including a fire that resulted in a fatality.
Bailey noted that an illegal dwelling at GreenPod Development had caught on fire in February as a result of an electrical problem.
“Our antenna’s up a little bit in making sure that structures out there are code compliant,” Bailey said.
The city also intended to be consistent about how rules were applied, Bailey said.
“I think our policy is the right thing to do,” Bailey said.
Beezley said EJFR hadn’t had “any particular surge” in the call volume and said call volume in general was lower compared to call volume at this time last year.
“There’s not a real spike in structure fires ... it’s been pretty calm for the last six months or so, at least,” Beezley said.
Beezley said that occasionally there was a higher report of fires in the winter due to reports of chimney fires.
SHORT ON STAFF
Bailey said another factor was that the city had been short a key building official staff member for six months. The position is now filled by Angela Garcia, whom Bailey said has now been working for the city for about a month.
But due to the time it took to fill that position, Bailey said, there had been a backlog of work building up.
“We moved this one up in our queue” to help the displaced tenant, Bailey said of fast-tracking the permit for the project at 535 Harrison St.
Bailey said that the workload for processing of permits varied, and that some builders put in their requests for permits well before work began.
IN FAVOR OF PROCESS
McCutcheon said he agreed with the safety goals of the permitting process.
“I totally agree with permits,” McCutcheon said of the permit process in general.
The permit fees were necessary to fund an important city service that ensures all work is done safely and up to code, McCutcheon said, “so we don’t have fires … building collapsing, that sort of of thing … You don’t Mickey Mouse it.”
He added, however, that “it’s not supposed to be a penalty type of thing.”
 
  • Like
Reactions: JBI
Our ordinance allows us to charge a double permit fee if work is started without a permit. I've only charged it once. Sounds like the city is being upfront in regards to the delay.
 
Double (and even triple) fees for working without a permit is common, it could've been an appearance ticket.
The contractor got caught, he got charged the statutory fees including the 'working without permit' penalty fee.
Maybe next time he'll have a conversation with the AHJ before exceeding allowable 'clean-up' and ordering the trusses?
 
A little different here. Disaster permits are free of charge. Fire, vehicles that run into buildings, hail storm damage, snow related roof collapses, wind damage, etc...
 
  • Like
Reactions: JBI
We double also for working without a permit, by ordinance. We are a bit more understanding with homeowners, but contractor are usually no mercy.

"Bailey said that trusses leaning against the building and materials placed on the roof “reasonably” led the building inspector to believe work was being done at the property."

I would be hard pressed to say this is working without a permit though. Stocking materials??

JMHO
 
The complaints resonate with personal experiences. Unnecessary fees, excessive delays, plan checker raising unwarranted planning issues. Suggest that this is why some do work without a permit.
 
Just as a follow up to the free disaster permits we do here in Gillette the thought behind us doing that was that the property owner had already suffered loss. So we had to ask our self the question if we were just throwing salt on an open wound? We wanted to do our part to help the owner recover as quickly and as economically as possible. This is a win, win for all. They recover faster and we get compliance with current codes. If they do emergency repairs no big deal. We can permit after the fact with no penalties no fees.
 
  • Like
Reactions: JBI
"EJFR fire investigator Wayne Kier wrote that the probable cause of the fire was that someone had placed an incandescent bulb of the incorrect size into a ceiling light fixture in the kitchen. The light fixture overheated, causing insulation in the attic to catch on fire, Kier wrote."

What kind of insulation catches on fire?
 
I don't get to see the cause of fire reports, the FD here just sez the fire started over there or in that area. I'm sure everybody's FD has an expert fire investigator that can pinpoint the exact cause of the fire, like insulation? or the UL label that sez 40 watt or less after it melts due to the fire, maybe they had enough of the light fixture to determine the brand and make?

What kind of insulation catches on fire?

Insulation with paper on it I suspect?
 
"EJFR fire investigator Wayne Kier wrote that the probable cause of the fire was that someone had placed an incandescent bulb of the incorrect size into a ceiling light fixture in the kitchen. The light fixture overheated, causing insulation in the attic to catch on fire, Kier wrote."

What kind of insulation catches on fire?



Some burns

Some have paper that burns


Check the flame spread and smoke de elopement on the so called non combustible
 
BTW, I also took issue with the doubling of the plan review fee...........I think that is really out of bounds.
 
We double also for working without a permit, by ordinance. We are a bit more understanding with homeowners, but contractor are usually no mercy.

Same here. We have a few contractors after the second one we will triple fee them. We only give a brake on the demo permits they ALL are only $5.
 
My AHJ has a policy on how to handle work done without a permit. I'm not sure what it is as it depends on which way the wind is blowing.
 
I thought it was clear in IBC Chapter 1 that "emergency repairs" could commence soon after (1) Permit Application. And that repair work would occur before and after the (2) Building Permit is Issued. But maybe that it simply how we do things around here. We do not double fee contractors as much as we should. We target those contractors who have a history of trying to do work without a permit. They seem to think that paying double fees on one or two projects each year is better than paying normal permit fees and all of their projects - those projects that stay under our radar.
 
I thought it was clear in IBC Chapter 1 that "emergency repairs" could commence soon after (1) Permit Application. And that repair work would occur before and after the (2) Building Permit is Issued. But maybe that it simply how we do things around here. We do not double fee contractors as much as we should. We target those contractors who have a history of trying to do work without a permit. They seem to think that paying double fees on one or two projects each year is better than paying normal permit fees and all of their projects - those projects that stay under our radar.
Pretty hard to double fees in California, and some other states, that limit fees to the cost of delivery of services.
 
I can relate to the problems. It took me several weeks to get a permit to replace window sashes on my house.

I was prevented from doing an over the counter review because I was not a contractor and because I was not acting as an owner builder. I wanted to get signoff and then have the contractor pick up the permit. If I had left it to the contractor they would have rolled over and it would have cost me an additional $3,000.

The end result after I talked with the plan checkers supervisor was that the plan check comments were found not relevant.

From what I have seen I do not believe this sort of problem is uncommon.

It is also my experience that plumbing contractors do not get permits even when required by the code because of the delays and the time it would take them at the building department.
 
Pretty hard to double fees in California, and some other states, that limit fees to the cost of delivery of services.
There are some added services that we are taking into account when we find construction without a permit and double the fee. I should point out that fees are only doubled when a knows they need a permit for the work they are doing (as in they have gotten a permit in the past) and have neglected to get one.

2 additional inspections
additional paperwork/records
The remaining inspections must be more rigorous as the contractors has been proven to be "untrustworthy"

That being said, the fees must be reasonable to start with...
 