Good evening all.
I’m wondering what you might think about the following, pertaining to the phasing of a project for a new market. The applicable code is the 2010 CBC (based on the 2009 IBC) and the 2010 CFC (based on the 2009 IFC).
The new building will be built next to an existing market, which will be demolished to make a parking lot, once the new building is complete. After the demo, the FSD to the side lot line would be >30’. The owner wants to have the market shut for the shortest possible time, and, therefore would like to request a temporary CofO as soon as the new building is finished. If granted, he could move the stock out of the old building into the new and open the store, while the demo and parking lot were being completed, maybe 6 weeks max.
The question is whether you would want to apply 705.3 during this period, when the existing building would have been vacated and would be under the control of a contractor with a demo permit. If so, the FSD would be temporary reduced. If the frontage allowance per 506.2 were calculated with this reduced FSD, then the building would be a bit over the max permitted area. If Table 705.8 were applied using the reduced FSD, then the opening area in the wall of the new building would exceed the max permitted. Phasing would require changing the construction type and protecting the openings, or the store would have to stay shut longer.
The wall of the existing building that would face the new building has no openings, and is double skin clay brick, and has a parapet. All required fire exits would be fully code compliant before the new store opened, ADA would be OK, parking etc would be OK, the only issues would be with the permitted floor area, and the area of the openings.
Would you go with a temporary CofO to allow the store to open before the demo was complete, or not?
Thanks
I’m wondering what you might think about the following, pertaining to the phasing of a project for a new market. The applicable code is the 2010 CBC (based on the 2009 IBC) and the 2010 CFC (based on the 2009 IFC).
The new building will be built next to an existing market, which will be demolished to make a parking lot, once the new building is complete. After the demo, the FSD to the side lot line would be >30’. The owner wants to have the market shut for the shortest possible time, and, therefore would like to request a temporary CofO as soon as the new building is finished. If granted, he could move the stock out of the old building into the new and open the store, while the demo and parking lot were being completed, maybe 6 weeks max.
The question is whether you would want to apply 705.3 during this period, when the existing building would have been vacated and would be under the control of a contractor with a demo permit. If so, the FSD would be temporary reduced. If the frontage allowance per 506.2 were calculated with this reduced FSD, then the building would be a bit over the max permitted area. If Table 705.8 were applied using the reduced FSD, then the opening area in the wall of the new building would exceed the max permitted. Phasing would require changing the construction type and protecting the openings, or the store would have to stay shut longer.
The wall of the existing building that would face the new building has no openings, and is double skin clay brick, and has a parapet. All required fire exits would be fully code compliant before the new store opened, ADA would be OK, parking etc would be OK, the only issues would be with the permitted floor area, and the area of the openings.
Would you go with a temporary CofO to allow the store to open before the demo was complete, or not?
Thanks