Have you ever seen the rebar in a slab floor cut at diagonals before the concrete pour?
This seems odd to me, but I called the structual engineer and he said he had told the general to do the cuts. It is typical to see the concrete cut for control joints but this was the first I have seen the rebar cut after it was tied and ready for pour.
Has anyone seen this before?