jakesktm
Registered User
Owner/Builder and Contractor [California]
Purchased a turn of the century home built in 1904. Pulled a permit to lift the home in place (the home was originally built as a balloon framed single story resting on 6' pier block with a brick stem wall foundation) and add a 2/1 unit (attached) underneath existing home (and all that it entails - new foundation, plumbing, electrical, mechanical to the ground). City was between building inspectors at the time and hired third party inspectors the whole time.
Company Z conducted the final inspection and the city issued a Certificate of Habilitability in 2019.
The house has been rented out since.
Fast forward to 2023.
I needed to replace the A/C units (window units) on the west facing bedrooms upstairs and pulled a permit to replace them with a 2-zone mini split. The front bedroom wall had no insulation I discovered so I began a partial demo to expose the wall so I could insulate. Company Z inspector drove by and red tagged the work saying I needed a demo permit. I didn't argue, apologized for my ignorance and went down the same day and paid the red tag fine and pulled a separate demo permit as he requested. His reasoning was that he wanted to see what was behind the wall. He also wanted the sheetrock tested for asbestos which came back negative.
I scheduled an inspection after removing the 100 sq feet of sheetrock, 10:00-11:00 am - The inspector no-showed. I called he didn't answer. I had to leave the job site.
I re-scheduled but could not be onsite the day he was available and left the unit accessible for the inspector. He showed up but said he couldn't get in. We rescheduled a third time. He no showed the third time with no phone call, nothing. I went down to the city building department and the clerk said the inspector wanted a $66 re-inspection fee.
At this point things went south. I told the building dept. manager the inspector no showed without notice so "no I'm not paying a re-inspection fee."
Inspector Z writes a scathing email calling me a liar and copies the email to all the city admin.
I respond to the email stating the above facts and asking for a new inspection date and request to meet with my contractor associate onsite.
The inspector shows up with a city police escort (I cannot make this up), and proceeds to tell my associate "he shouldn't have called me a liar" (for the record I never called him out as a liar, I just stated the problem).
He then proceeds to attack the 2019 Final Inspection (despite him being the inspector on the final) and wants me to open up walls, get engineering approvals, provide building plans, and that he will need to review the entire project again before I can proceed with the work. Zero inspection of the demo permit.
I have relayed my concerns to the city administration none of whom want to sit down and discuss. Instead I was offered to talk with the owner of Company Z.
What should I do at this point? Is it legal for the inspector to re-open an investigation into a project that has already been finaled and issued a certificate of habitability? What role does the city have to become involved?
Purchased a turn of the century home built in 1904. Pulled a permit to lift the home in place (the home was originally built as a balloon framed single story resting on 6' pier block with a brick stem wall foundation) and add a 2/1 unit (attached) underneath existing home (and all that it entails - new foundation, plumbing, electrical, mechanical to the ground). City was between building inspectors at the time and hired third party inspectors the whole time.
Company Z conducted the final inspection and the city issued a Certificate of Habilitability in 2019.
The house has been rented out since.
Fast forward to 2023.
I needed to replace the A/C units (window units) on the west facing bedrooms upstairs and pulled a permit to replace them with a 2-zone mini split. The front bedroom wall had no insulation I discovered so I began a partial demo to expose the wall so I could insulate. Company Z inspector drove by and red tagged the work saying I needed a demo permit. I didn't argue, apologized for my ignorance and went down the same day and paid the red tag fine and pulled a separate demo permit as he requested. His reasoning was that he wanted to see what was behind the wall. He also wanted the sheetrock tested for asbestos which came back negative.
I scheduled an inspection after removing the 100 sq feet of sheetrock, 10:00-11:00 am - The inspector no-showed. I called he didn't answer. I had to leave the job site.
I re-scheduled but could not be onsite the day he was available and left the unit accessible for the inspector. He showed up but said he couldn't get in. We rescheduled a third time. He no showed the third time with no phone call, nothing. I went down to the city building department and the clerk said the inspector wanted a $66 re-inspection fee.
At this point things went south. I told the building dept. manager the inspector no showed without notice so "no I'm not paying a re-inspection fee."
Inspector Z writes a scathing email calling me a liar and copies the email to all the city admin.
I respond to the email stating the above facts and asking for a new inspection date and request to meet with my contractor associate onsite.
The inspector shows up with a city police escort (I cannot make this up), and proceeds to tell my associate "he shouldn't have called me a liar" (for the record I never called him out as a liar, I just stated the problem).
He then proceeds to attack the 2019 Final Inspection (despite him being the inspector on the final) and wants me to open up walls, get engineering approvals, provide building plans, and that he will need to review the entire project again before I can proceed with the work. Zero inspection of the demo permit.
I have relayed my concerns to the city administration none of whom want to sit down and discuss. Instead I was offered to talk with the owner of Company Z.
What should I do at this point? Is it legal for the inspector to re-open an investigation into a project that has already been finaled and issued a certificate of habitability? What role does the city have to become involved?