• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

projection

  1. S

    Modern stair tread code interpretation

    Hi all, We're having a code disagreement in our office I was hoping you could weigh in on. Does the stair design in the image attached meet the IRC 2021 (Connecticut)? The intention is for the stair to have a modern design, with no squared off nosing projection, with a tread depth less than...
  2. S

    70 mm thick solid masonry units maximum projection?

    These are from Ontario building code: -------------------------------------------------------------------------------------------------------------------------------------- 9.20.8.5. Projection of Masonry Veneer Beyond Supporting Members (1) Masonry veneer of solid masonry units resting on a...
  3. D

    Handrail Projection

    Per NYC Building Code 1012.8, handrails can project into the required width of stairways or ramp up to 4 1/2". Does this projection include the vertical post that supports the handrails? The posts will be mounted to the ground and located 60" O.C. This is an exterior application. Thoughts?
  4. A

    Oversized egress paths with secondary uses.

    Something our office hasn't run into before- Project is a 7000sf restaurant: The owner wants hand wash sinks outside of the WC in a rear hall which also serves egress. The minimum path width is 3'9" the hall is 5'1" wide, and the proposed sinks are 14" deep- so there is no projection into the...
Top