Existing multi-tenant building 60% occupied.
Current tenant space has 100 amp panel in unit. All meters are in separate electrical room.
New tenant has proposed using a vacated 3 phase service from the electrical room, and running an additional service to the tenant space.
His plan is to rework the existing 100 amp for existing lighting and convenience circuits, and use the new 3 phase for his proposed addition of deli coolers and refrigerators.
Space will then be serviced by 2 meters.
Any input is appreciated.
2006 IBC
2005 NEC
mj
Existing multi-tenant building 60% occupied.
Current tenant space has 100 amp panel in unit. All meters are in separate electrical room.
New tenant has proposed using a vacated 3 phase service from the electrical room, and running an additional service to the tenant space.
His plan is to rework the existing 100 amp for existing lighting and convenience circuits, and use the new 3 phase for his proposed addition of deli coolers and refrigerators.
Space will then be serviced by 2 meters.
Any input is appreciated.