california kid
Member
- Joined
- Jul 4, 2011
- Messages
- 8
I am new to the world of fire sprinkler design and find myself at a quandry. Im working on a design that requires 31.04 gpm @ 25.949psi with a safty margin of 16.044psi. These calcs were run with a 1" pvc run from the meter to the riser. All of the house's around here that i have looked at (some on the same block, similar in size, and with flat ceilings) have 1 1/4" to 2" runs to the riser. I have triple checked my information but cant shake the feelin im missing something....could this just be a case of bigger is better?