Seeing a new thing that doesn't make much sense to my simple mind. Mechanical system has "barometric relief ducts" to the outside. Basically a register inside the room to convey conditioned air to the outside at the eaves. Not on the original plan, I requested a revision to the mech. plans as well as revised comcheck. I got a revision to the mech plans with no mention of how it impacts the energy efficiency. I am told by the contractor they have been added to the system because they are supplying more than they are returning to the rooms, and that they will dump the excess supply outside. Anybody seen anything like this? I don't understand how this could possibly be energy efficient. If it matters, type V, B occ., private daycare/learning facility.