Generally, I get a fairly reasonable estimate from the contractor for the materials and labor for a project.
My question to you is, how would you handle fees for a permit submitted by the homeowner for a project and only the cost of materials is listed?
Do you use the valuation table? If you know the valuation for a similar building - i.e. shed, garage, etc., - would you use this to determine the appropriate fees?
Reason for the question is I have an application for a 24' x 36' garage for $10K, no labor cost listed. I was quoted $15K for a similar 24' x 36' garage built by a contractor.
TIA,
My question to you is, how would you handle fees for a permit submitted by the homeowner for a project and only the cost of materials is listed?
Do you use the valuation table? If you know the valuation for a similar building - i.e. shed, garage, etc., - would you use this to determine the appropriate fees?
Reason for the question is I have an application for a 24' x 36' garage for $10K, no labor cost listed. I was quoted $15K for a similar 24' x 36' garage built by a contractor.
TIA,