1704.2.4 Report requirement. Approved agencies shall keep
records of special inspections and tests. The approved agency
shall submit reports of special inspections and tests to the
building official and to the registered design professional in
responsible charge. Reports shall indicate that work inspected
or tested was or was not completed in conformance to
approved construction documents. Discrepancies shall be
brought to the immediate attention of the contractor for correction.
If they are not corrected, the discrepancies shall be
brought to the attention of the building official and to the registered
design professional in responsible charge prior to the
completion of that phase of the work. A final report documenting
required special inspections and tests, and correction of
any discrepancies noted in the inspections or tests, shall be
submitted at a point in time agreed upon prior to the start of
work by the owner or the owner’s authorized agent to the
building official.