• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

Emergency System must be Commissioned and Not Just Tested - 2023 NEC

jar546

Forum Coordinator
Joined
Oct 16, 2009
Messages
11,087
Location
Somewhere Too Hot & Humid
Here is the verbiage of the 2023 NFPA 70 for Emergency Systems

700.3 Tests and Maintenance.
(A) Commissioning Witness Test.
The authority having jurisdiction shall conduct or witness the commissioning of the complete system upon installation and periodically afterward.
Informational Note:
See NECA 90, Standard for Commissioning Building Electrical Systems.
 