• Welcome to The Building Code Forum

    Your premier resource for building code knowledge.

    This forum remains free to the public thanks to the generous support of our Sawhorse Members and Corporate Sponsors. Their contributions help keep this community thriving and accessible.

    Want enhanced access to expert discussions and exclusive features? Learn more about the benefits here.

    Ready to upgrade? Log in and upgrade now.

Fire Partition Walls- details

Stepheneckert

REGISTERED
Joined
Dec 16, 2022
Messages
1
Location
Boulder , CO
I'm working on a 10 unit stacked flat- three story residential building. It requires a 1 hour fire partition wall, NOT a fire wall between units. We are using AAC (autoclaved concrete blocks) as the partition wall continuous from foundation through to parapets. The structure is not isolated- meaning all floors bear on the same wall side to side- not a double wall. My questions is will this work? My structural engineer says we cant do that- we need to isolate the structure on both sides. I'm pretty sure he is wrong, I just cant 100% prove it. Anyone know the answer? Thanks!!

Stephen
 
2021 IBC 420.2 requires the separation walls to be built as fire partitions in accordance with Section 708. There is nothing in that about separate structures. I will say, though, I almost always see the unit separation wall done as two stud walls.
 
In Canadian Codes, insetting joists into a concrete/masonry/block wall with a fire rating is acceptable, as long as the remaining material is sufficient to provide the required fire-resistance rating.
In our system, we have a fairly intense formulaic process for calculating FRR of common assemblies independent of ULC testing (Appendix D). I have no idea what IBC/ICC might allow, but in Canadian code, three inches of type S mortar/concrete is sufficient to provide one hour of FRR.
 
I'm working on a 10 unit stacked flat- three story residential building. It requires a 1 hour fire partition wall, NOT a fire wall between units. We are using AAC (autoclaved concrete blocks) as the partition wall continuous from foundation through to parapets. The structure is not isolated- meaning all floors bear on the same wall side to side- not a double wall. My questions is will this work? My structural engineer says we cant do that- we need to isolate the structure on both sides. I'm pretty sure he is wrong, I just cant 100% prove it. Anyone know the answer? Thanks!!

Stephen
What is his code section?
 