mtlogcabin
SAWHORSE
I have 3 story R-2, V-A building with a NFPA 13R system, 2006 IBC
There are some steel columns and beams the I-joist floor system will be hanging from using top flange hangers. The contractor was informed by the fire spray applied fire proofing contractor that the I-Joist hangers need to be fire proofed also since they are steel. The GC is asking if this is required now. Never heard of having to do this.
There are some steel columns and beams the I-joist floor system will be hanging from using top flange hangers. The contractor was informed by the fire spray applied fire proofing contractor that the I-Joist hangers need to be fire proofed also since they are steel. The GC is asking if this is required now. Never heard of having to do this.