I'm a California guy, still getting used to the IBC. I have a new "flat-roofed" building with exterior wall parapets to aid in directing the roof drainage and aesthetics (to hide some rooftop equipment). The building is type V-A wood-framed apartments (one-hour construction). The parapet is NOT used as a fire wall, it is atop the exterior walls, and per CBC/IBC 704.11 exc. #1 a parapet is not required due to location on property.
QUESTION: If I'm not required to provide a parapet for code reasons, but I provide one anyway for aesthetic reasons, does the parapet still have to be one-hour rated? (e.g. per CBC 704.11.1)
The plan checker is making me sheath the back side of the parapet with Type X gyp board over my plywood sheathing before applying the modified bitument roofing up the wall. I would rather not put gyp board here.
QUESTION: If I'm not required to provide a parapet for code reasons, but I provide one anyway for aesthetic reasons, does the parapet still have to be one-hour rated? (e.g. per CBC 704.11.1)
The plan checker is making me sheath the back side of the parapet with Type X gyp board over my plywood sheathing before applying the modified bitument roofing up the wall. I would rather not put gyp board here.