Fatal mistakes are sometimes a real surprise. This work is set up with girder pockets but the dirt inside the footing is too high. To achieve the required 12" clearance to dirt. So much dirt will have to be removed that the required depth into undisturbed soil will be short by 8". The forms and steel will come out to enable them to dig deeper so am I wasting my time by writing a host of corrections?
The other setback is the service drop. They will need a temporary power pole before they start framing.
The other setback is the service drop. They will need a temporary power pole before they start framing.