Good Afternoon,
We have recently had a rush of pool contractors saying they are not going to replace glazing within 5' of the waters edge. They would like to use R308.4.3, Exception 2. They will install a rail 34"-38" above the walking surface. They say this makes the glazing no longer in a hazardous location, and our part-time BO is looking like he will approve it.
I say R308.4.3 and any exceptions found within have nothing to do with R308.4.5, which deals with glazing and wet surfaces.
Have any of you out there approved a handrail or guard instead of making the contractor replace the window or add an approved product to the existing glazing? If so, would a single horizontal rail be sufficient to you?
Thank you!
We have recently had a rush of pool contractors saying they are not going to replace glazing within 5' of the waters edge. They would like to use R308.4.3, Exception 2. They will install a rail 34"-38" above the walking surface. They say this makes the glazing no longer in a hazardous location, and our part-time BO is looking like he will approve it.
I say R308.4.3 and any exceptions found within have nothing to do with R308.4.5, which deals with glazing and wet surfaces.
Have any of you out there approved a handrail or guard instead of making the contractor replace the window or add an approved product to the existing glazing? If so, would a single horizontal rail be sufficient to you?
Thank you!