REGISTERED
i'm used to seeing sprinkler mains used as the water service for the grounding electrode system, hence tieing the gec to it. now, i'm in a new area, working as an inspector, local FM says that this practice is in direct conflict w/ NFPA 13 and wont allow it , i don't have NFPA docs at my finger tips. even if it was in conflict, wouldn't the more stringent code rule apply here? water service is all pex in this area.
numero dos, on a service, conduit runs from main dp to a sub panel, bonding bushings are re3q'd at BOTH ENDS OF THE CONDUIT right? thanks in advance
numero dos, on a service, conduit runs from main dp to a sub panel, bonding bushings are re3q'd at BOTH ENDS OF THE CONDUIT right? thanks in advance