Builder Bob
SAWHORSE
Just a question or two, We have a single occupant hyperbaric chamber being installed in out jurisidiction. Since this is new to us (all the others have been installed in hospitals and fell under the State's Health Department Inspections, I was wanting to know if I have overlooked anything - Chapter 27, 32, and 40 of the IFC, NFPA 55 & NFPA 99 for the bulk storage of oxygen and NFPA 99 for the hyperbaric chamber - single occupant.
The main question that I have is for the room containing the hyperbaric chamber, does it have to be 1 hour fire rated construction?
(Note V-B construction, limited area sprinkler is being offered for the room containing the hyperbaric chamber)
The main question that I have is for the room containing the hyperbaric chamber, does it have to be 1 hour fire rated construction?
(Note V-B construction, limited area sprinkler is being offered for the room containing the hyperbaric chamber)
Last edited by a moderator: