• Welcome to the new and improved Building Code Forum. We appreciate you being here and hope that you are getting the information that you need concerning all codes of the building trades. This is a free forum to the public due to the generosity of the Sawhorses, Corporate Supporters and Supporters who have upgraded their accounts. If you would like to have improved access to the forum please upgrade to Sawhorse by first logging in then clicking here: Upgrades

IPC 308.6 Sway Bracing - Explained

jar546

Forum Coordinator
Joined
Oct 16, 2009
Messages
11,064
Location
Somewhere Too Hot & Humid
Here’s an educational summary of IPC code section 308.6 on sway bracing:
  • Scope of the Code: Applies to horizontal drainage or waste pipes that are 4 inches (102 mm) or larger.
  • Conditions for Bracing:
    • Bracing is required where a pipe fitting changes the flow direction by more than 45 degrees.
    • This is to counteract the forces generated by the change in flow direction, which could otherwise move the pipe.
  • Nature of Flow and Forces:
    • Wastewater flow in large pipes (4 inches and larger) can surge significantly, especially when multiple smaller branches discharge into them.
    • These surges create waves of high flow, impacting fittings and potentially causing movement in the direction of flow.
  • Consequences of Unbraced Fittings:
    • Direction-changing fittings may move, pulling the upstream piping with them.
    • This lateral movement can lead to "swaying" of downstream piping, potentially causing failure in pipe couplings and connections.
  • Rationale for Bracing:
    • Rigid bracing or similar supports are mandated to prevent the upstream pipe and its fittings from moving in the direction of flow.
    • This ensures the downstream piping remains stable and does not sway sideways.
  • Exceptions to Bracing Requirements:
    • Upstream bracing is not required where the flow direction changes into a vertical pipe. Vertical pipes are supported differently and do not sway side to side.
    • The code does not apply to buried piping, as the backfill provides necessary support to prevent movement.
 