I just got a submittal for a building where the DP is claiming that parts of the same suite are different levels of alteration. For example, they claim 251s.f. of level 2, 1521s.f. level 1 and 2,474s.f. of repair. For starters, I am not sure how this would help, but I also don't think it is a correct application of the code. To me, if a space is reconfigured to any extent, level 1 is not a viable option. I have little experience with this code and haven't encopuntered this before. Any opinions as to why it would be submitted this way and if it is in line with the IEBC?