805.1 states, "The requirements of this section shall be limited to work areas that include exits or corridors shared by more than one tenant within the work area in which Level 2 alterations are being performed..."
In this context what is the definition of tenant?
If there is one tenant does that mean 805 doesn't apply and the next step is to default to 704.1?
Specifically:
Level 2 alteration project wants to add square footage (group A-2) to a fourth story. The problem is there is only one exit on the fourth level and it is technically infeasible to add a second exit.
In this context what is the definition of tenant?
If there is one tenant does that mean 805 doesn't apply and the next step is to default to 704.1?