ICC IFC 2006 = adopted code
Existing building, old library, 9,710 square footage gross, max occupancy based on 1004.1.1 tabe = 194 (worst case scenario). Egress capacity is 650,
changed to dance hall, same gross square footage, based on 1004.1.1 now occupancy exceeds egress capacity, A-3 > 300 capacity must be sprinkled. Some are saying post occupancy of 300 unsprinkled, others say sprinkle building and post occupancy of 650, others are saying sprinkle the building and make egress capacity meet or exceed occupancy per 1004.1.1.
What is correct?
Thanks,
Richard
Existing building, old library, 9,710 square footage gross, max occupancy based on 1004.1.1 tabe = 194 (worst case scenario). Egress capacity is 650,
changed to dance hall, same gross square footage, based on 1004.1.1 now occupancy exceeds egress capacity, A-3 > 300 capacity must be sprinkled. Some are saying post occupancy of 300 unsprinkled, others say sprinkle building and post occupancy of 650, others are saying sprinkle the building and make egress capacity meet or exceed occupancy per 1004.1.1.
What is correct?
Thanks,
Richard