BayPointArchitect
Sawhorse
Does anyone know where I can find a standard detail that illustrates how these are installed?
I have a particular concern that when the trench is filled with concrete to provide minimum 2" cover all around...
the pvc lined metal duct with become buoyant and pop up out of the concrete with no hope for setting it back into place. So how do these underground ducts get anchored down?
Thanks
ICC Certified Plan Examiner
Registered Architect
I have a particular concern that when the trench is filled with concrete to provide minimum 2" cover all around...
the pvc lined metal duct with become buoyant and pop up out of the concrete with no hope for setting it back into place. So how do these underground ducts get anchored down?
Thanks
ICC Certified Plan Examiner
Registered Architect