They requested a sheathing inspection so they can dry in the roof. The two guys at the other end were still framing the roof. I don't think the vent material is available any longer so the vent must be changed. The GC will have the framer change it.TheCommish said:did they say they were ready for an inspection? I would call it a progress inspection and use it as a teaching moment, not a gotucha