Finally got the connection details for a solar panel (photovoltaic) roof installation. Brackets are to be secured with a 5/16 lag with minimum 1.8" embedment into the rafter (I don't recall the uplift capacity).
The problem (or maybe it's not a problem) is the roof rafters are TJI Trus-Joists. Pitch about 3:12.
Any issues with using the top cord as an anchorage point? Seems to me these are not designed to work in tension, but I may just be overthinking.
We're in a 120mph wind zone.
Thanks!