mtlogcabin
SAWHORSE
Here is a link to loading the bottom tji flanges. The withdrawl loads will work for uplift on the top cords. It is the diameter and depth of threads you need to be concerned with. Also note the installer needs to be pre-drilling the holes for the fasteners. This is just I-levels literature you should be able to get the same info from whoever manufactured the I-Joist that is installed.
http://www.ilevel.com/literature/TB-808.pdf
http://www.ilevel.com/literature/TB-808.pdf
That is the point that the chord to web connection will failI called the technical department for Trus-Joist and explained the situation.Rep stated the chord-to-web connection is rated for 500 lbs at any point.
Last edited by a moderator: