No Soup for you
REGISTERED
I did a search but couldn't find
Looking for some input as to what you guys do.
I have had a bunch of these lately. Mostly they are trying to avoid the variance process which I really cant blame them.
The other Building Inspector here says its ok to leave one wall and I want them to remove and replace one wall (and footings if needed etc.) at a time.
Technically they are "making repairs" to the existing non conforming structure. (as long as it is same footprint)
A couple of times the one wall they were supposed to leave, we go out and its gone.
Then we get the contractor saying.... well... it fell down, it was too damaged to leave etc... blah blah blah
Just asking for some thoughts on what you guys do/allow.
Looking for some input as to what you guys do.
I have had a bunch of these lately. Mostly they are trying to avoid the variance process which I really cant blame them.
The other Building Inspector here says its ok to leave one wall and I want them to remove and replace one wall (and footings if needed etc.) at a time.
Technically they are "making repairs" to the existing non conforming structure. (as long as it is same footprint)
A couple of times the one wall they were supposed to leave, we go out and its gone.
Then we get the contractor saying.... well... it fell down, it was too damaged to leave etc... blah blah blah
Just asking for some thoughts on what you guys do/allow.