I have a proposal for a new USFS building here in town, 24,000 sq. ft. We had a meeting two weeks ago with the builder and their engineer to hash out the planning and zoning requirements to present to the Planning Commission. This will be a LEED certified building per the contract.
During the discussion, it was mentioned that they want to do the shell first with one permit. The shell will be a metal building with rock fascia approximately 4 foot high on all walls.
The second phase would be the TI and under a second (maybe more) permit(s). This will start after the building is built.
I have serious concerns over the whole project because of the parties involved. The last developement (mini-mall) that was done this way is still not complete 4 years later.
My questions are:
1) Can I require them to to do this under 1 permit and not multiple?
2) As this is a LEED certified building, doesn't it need to be under one permit to get the LEED certification?
Thanks in advance for your input.
During the discussion, it was mentioned that they want to do the shell first with one permit. The shell will be a metal building with rock fascia approximately 4 foot high on all walls.
The second phase would be the TI and under a second (maybe more) permit(s). This will start after the building is built.
I have serious concerns over the whole project because of the parties involved. The last developement (mini-mall) that was done this way is still not complete 4 years later.
My questions are:
1) Can I require them to to do this under 1 permit and not multiple?
2) As this is a LEED certified building, doesn't it need to be under one permit to get the LEED certification?
Thanks in advance for your input.