I have an existing manufacturing/office building project last renovated under the 1991 Uniform Building Code. At that time the occupancy for manufacturing fell under Business, Division 2.
Now under the 2012 IEBC we will be doing a Level 2 Alteration. My understanding is that existing construction can be left as-is if it's not unsafe, but new work should comply with the 2012 IBC.
So under the 2012 IBC, manufacturing would now be a Factory occupancy, F-1.
Do I follow the requirements for Factory occupancy or Business occupancy for the new work?
Now under the 2012 IEBC we will be doing a Level 2 Alteration. My understanding is that existing construction can be left as-is if it's not unsafe, but new work should comply with the 2012 IBC.
So under the 2012 IBC, manufacturing would now be a Factory occupancy, F-1.
Do I follow the requirements for Factory occupancy or Business occupancy for the new work?