I have a project whereby an existing 4 unit apartment building (not sprinklered) is going to do an extensive remodel (bringing the entire building to studs and removing all exterior wall coverings) ((oh and this building is 4" from the adjacent property line))
3404.1 says basically unless excepted elsewhere in this section, alterations shall comply with the requirements of the code for new construction. Alterations shall be such that the existing building or structure is no less complying with the provisions of this code than the existing building or structure prior to the alteration".
1. I'm having difficulty with the bold section above. Does this mean it has to comply with provisions for new construction or not? To me, it reads that it needs to comply with new but not beyond that?
2. I can't find any exception to waive the sprinklers that are required by section 903.2.8.
Due to proximity to the property line and the fact that this is a project involving reconstruction of over 50% of the building, my gut (and from what I'm thinking I'm getting out of Chapter 34) is to require one hour walls (with appropriate opening limitations/protection) on the wall 4" from the property line and sprinklers. I want to make sure that I'm not missing some exceptions or other paths they can take though. I know they can use the IEBC, but not sure that will help in this case?
3404.1 says basically unless excepted elsewhere in this section, alterations shall comply with the requirements of the code for new construction. Alterations shall be such that the existing building or structure is no less complying with the provisions of this code than the existing building or structure prior to the alteration".
1. I'm having difficulty with the bold section above. Does this mean it has to comply with provisions for new construction or not? To me, it reads that it needs to comply with new but not beyond that?
2. I can't find any exception to waive the sprinklers that are required by section 903.2.8.
Due to proximity to the property line and the fact that this is a project involving reconstruction of over 50% of the building, my gut (and from what I'm thinking I'm getting out of Chapter 34) is to require one hour walls (with appropriate opening limitations/protection) on the wall 4" from the property line and sprinklers. I want to make sure that I'm not missing some exceptions or other paths they can take though. I know they can use the IEBC, but not sure that will help in this case?