Hi,
Got some good knowledge on my post last week, and one of the guys said I should post this out there for opinions.
The city currenly came in and said we are B1/S2, thus wanted us to put up a 2 hour Fire Barrier which I am showing (solid black line) that my architect created.
My concern is am I S2 or S1. We store alloy wheels in cardboard boxes. I see metal parts in S2 that can be stored in thin paper but see cardboard in S1.
With this B1/S2 means I need the fire barrier. But with this I can expand up to like 17000 sq ft.
With B1/S1 means no fire barrier. I can go 12000 sq ft (is this overall or just in S1?)




Got some good knowledge on my post last week, and one of the guys said I should post this out there for opinions.
The city currenly came in and said we are B1/S2, thus wanted us to put up a 2 hour Fire Barrier which I am showing (solid black line) that my architect created.
My concern is am I S2 or S1. We store alloy wheels in cardboard boxes. I see metal parts in S2 that can be stored in thin paper but see cardboard in S1.
With this B1/S2 means I need the fire barrier. But with this I can expand up to like 17000 sq ft.
With B1/S1 means no fire barrier. I can go 12000 sq ft (is this overall or just in S1?)