So, well, I have inherited a large development project when I came on board here some months ago. It is a single site development with multiple buildings. The permit was issued as a single permit for all buildings. While one building is 98% completed as a shell and core, the other building shell and core will take another 3-6 months. But the tenant that will be occupying the first wants to take control ASAP to start the interior build out. So, since this entire project is a single permit I don't think I can issue a Temporary CO as the list of items left for the entire development would be pretty extensive. Is there a Partial CO that could be issued? Or even actually a Partial Temporary CO since there will be items such as landscaping and a few site improvements which won't happen until early next spring?
Ideas?