• Welcome to The Building Code Forum

    Your premier resource for building code knowledge.

    This forum remains free to the public thanks to the generous support of our Sawhorse Members and Corporate Sponsors. Their contributions help keep this community thriving and accessible.

    Want enhanced access to expert discussions and exclusive features? Learn more about the benefits here.

    Ready to upgrade? Log in and upgrade now.

Complete Retrofit of 1939 House Roof / Ceiling

jar546

CBO
Joined
Oct 16, 2009
Messages
12,816
Location
Not where I really want to be
This is on a barrier island the house has existing since 1939 and is located in an exposure D 170mph wind zone. This is some of the framing changes underway.
click on photo to enlarge
IMG_0804.JPG
 
I would double check the engineer's registration. The bolt group on the rafter ties makes no sense whatsoever, not in arrangement or fastener selection, it has carpenter logic written all over it.
 
  • Like
Reactions: ICE
I would double check the engineer's registration. The bolt group on the rafter ties makes no sense whatsoever, not in arrangement or fastener selection, it has carpenter logic written all over it.
I can’t make the meeting, but my structural guy will be meeting with the engineer on the job site today at 1 PM. I went there this morning to spot check and found a few framing issues and some fire blocking issues that will be happening in the future, based on some of the double wall framing.
Maybe they are trying to meet the stupid energy code....
That is an easy code to meet in Florida.
 