if you have a 17000 sf shopping center shell building; 1 story; IIB construction; no sprinkler system; 60' clear on 3 sides and 32' clear on one side...
can you subdivide the tenant spaces into 4 restaurants (A-2 use) each separated by fire rated assemblies in order to NOT put in a fire sprinkler system per section 903.2.1.2 IBC 2006?
if you can do separations what is the rating of each separation as table 508.3.3 says no rating required for A use separations???
is the separation a fire barrier or a fire wall?
is the rating 1 hour per table 602?
can you subdivide the tenant spaces into 4 restaurants (A-2 use) each separated by fire rated assemblies in order to NOT put in a fire sprinkler system per section 903.2.1.2 IBC 2006?
if you can do separations what is the rating of each separation as table 508.3.3 says no rating required for A use separations???
is the separation a fire barrier or a fire wall?
is the rating 1 hour per table 602?