John DeBruyne
REGISTERED
A complex question (hence the bullet points to try and help with clarity):
Understandably, "grandfathered" construction needs to comply with the codes in effect at the time of construction, but any insight on this 25 year lapse or occupancy being allowed on the first floor without proper overall building fire-proofing would be appreciated. I don't think the 2015 Michigan Rehab Code provides any guidance.
- I have a client who purchased an existing A-3 indoor family amusement center (athletic field, laser tag, arcade, bounce house, gym, etc.) in 2011.
- The original building was constructed in 1998 (1993 BOCA) as a 2-story fire-suppressed Construction Type 2A building. Steel structure, open web steel roof joists, metal roof deck, precast concrete second floor, and non-bearing masonry infill exterior walls. 2A required to comply with Table 503 area limitations.
- The 2nd floor is open to the spaces below and is too big to be a mezzanine.
- The original plans indicated that the second floor was a "future use and plans would need to be submitted for permits and occupancy".
- One continuous roof at the same elevation covers the entire building. To comply with Table 602 roof construction requirements, the original plans indicated that the roof construction over the second floor was required to be protected with fire proofing. The roof construction over the roller hockey rink was high enough to not require fire proofing. The rest of the structural members are protected with fire proofing.
- For some reason that is unclear (municipality hasn't provide a clear reason), fire proofing was never provided at the roof above the second floor. Those who were involved in that decision are no longer available and records are not helpful. The only thing found was a report from the municipality noting that permits are required for second floor occupancy.
- In 2005, an intermediate building owner bought the building and submitted interior renovation plans which included occupancy of the second floor with laser tag. Permits were granted but no requirements for fire proofing the roof were noted. A temporary C of O was granted while permits were being closed out. The intermediate owner then went out of business in 2007 and permits were never closed out.
- Our client and current owner resumed occupancy when they bought the building in 2011, unaware of previous owner's permitting and occupancy issues.
- As building owner do, they made some relatively minor layout changes and changed the 2nd floor occupancy from laser tag to batting cages.
- The municipality became aware of the changes in 2024 and required our client to submit for permits. During a walk through, the municipality realized that fire proofing was never provided and is now requiring our client to provide it.
- Calculations using current 2015 Michigan Building Code would still require the building to be Type II-B and would require fire proofing.
Understandably, "grandfathered" construction needs to comply with the codes in effect at the time of construction, but any insight on this 25 year lapse or occupancy being allowed on the first floor without proper overall building fire-proofing would be appreciated. I don't think the 2015 Michigan Rehab Code provides any guidance.