Mech
REGISTERED
2009 IBC - Type IIB construction for Buildings 1 and 2.
How far must the fire wall extend from building line 2 towards building line 1?
Option 1: Does it stop at bldg line 2 with a 1 hour rated wall 4 ft long? Can this wall stop short of bldg line 1 since the fire separation distance from Building 2 is greater than 30 ft? Do I need to add a 1 hour rated 4 ft long wall along the canopy opening and perpendicular to the fire wall?
Option 2: Extend the fire wall to bldg line 1, then no other walls need to be rated?
How far must the fire wall extend from building line 3 towards building line 4?
Option A: Similar to Option 1 above. Does it stop at bldg line 3 with a 1 hour rated wall 4 ft long? Can this wall stop short of bldg line 4 since the fire separation distance from Building 1 is greater than 30 ft? Do I need to rate 4 ft of Building 2 wall for 1 hour along bldg line 3?
Option B: Extend the fire wall to bldg line 4, then Building 2 along bldg line 3 does not need to be rated? I assume then that the overhead door and personnel door would both need to be rated?
Am I making this more difficult than it is?
Thanks for the input!
How far must the fire wall extend from building line 2 towards building line 1?
Option 1: Does it stop at bldg line 2 with a 1 hour rated wall 4 ft long? Can this wall stop short of bldg line 1 since the fire separation distance from Building 2 is greater than 30 ft? Do I need to add a 1 hour rated 4 ft long wall along the canopy opening and perpendicular to the fire wall?
Option 2: Extend the fire wall to bldg line 1, then no other walls need to be rated?
How far must the fire wall extend from building line 3 towards building line 4?
Option A: Similar to Option 1 above. Does it stop at bldg line 3 with a 1 hour rated wall 4 ft long? Can this wall stop short of bldg line 4 since the fire separation distance from Building 1 is greater than 30 ft? Do I need to rate 4 ft of Building 2 wall for 1 hour along bldg line 3?
Option B: Extend the fire wall to bldg line 4, then Building 2 along bldg line 3 does not need to be rated? I assume then that the overhead door and personnel door would both need to be rated?
Am I making this more difficult than it is?
Thanks for the input!