El Ducci
REGISTERED
New floor joists over basement, 2x10 floor joists over 6x12 LVL center beam. Was expecting contractor to overlap the joists over LVL beam. When I arrived at job site, the joists have been butted end-to-end over LVL beam with a short piece of 2x10 "sistered" to one side of the abutment. Is this code compliant/will it pass inspection? Appreciative, ED