Darren Emery
Registered User
The concrete crew didn't know the builder planed on a door there - so the CEE ended up in the door opening. The CEE and clamp are flush with the floor surface, the GEC is under about 1/2" of concrete cover. Would you accept this in light of 2012 IRC E3610.2? BTW - GEC is #6 bare copper, just visible where it sneaks out under the door jack stud.