New Condo units... Type 5-B Construction - 2009 NFPA
Let's say we are specifying UL#- L528 Floor/CLG assembly (Wood trusses / resilient channels/ 5/8" Drywall).
Normal construction practice is to frame the interior walls before installing the drywall. Which means that the 5/8" Drywall at the ceiling would not be continuous were it meets the interior partitions walls. Our fire marshal wants an UL# that shows that providing a continuous blocking above the interior partitions (to allow for the drywall ceiling to be nailed) is an approved/tested method.
Anyway, I'm having a hard time finding that connection/detail on the UL book.
I already placed a call on UL-help and they are going to get back to me... but wanted to see if anyone else has run into a similar experience.
Thanks
Let's say we are specifying UL#- L528 Floor/CLG assembly (Wood trusses / resilient channels/ 5/8" Drywall).
Normal construction practice is to frame the interior walls before installing the drywall. Which means that the 5/8" Drywall at the ceiling would not be continuous were it meets the interior partitions walls. Our fire marshal wants an UL# that shows that providing a continuous blocking above the interior partitions (to allow for the drywall ceiling to be nailed) is an approved/tested method.
Anyway, I'm having a hard time finding that connection/detail on the UL book.
I already placed a call on UL-help and they are going to get back to me... but wanted to see if anyone else has run into a similar experience.
Thanks