2009 IEBC
Work is limited to two public use toilet rooms - changing floor and wall tile, changing plaster ceiling to gyp board, replacing toilet partitions and plumbing fixtures, changing light fixtures, changing HVAC grilles, and adjusting electrical switch height. There is no floor space reconfiguration except the possibility of shifting plumbing fixtures and partitions to meet IPC requirements.
Must ICC A117.1-2009 be followed in its entirety if not providing an accessible family or assisted-use toilet room (605.1.10)? The water closet compartments do not have the required floor spaces and without tearing down walls, they cannot be made compliant; also, compartment doors swing into the insufficient toilet clear floor spaces. If the door swing is reversed, then there will not be 18" clearance on the latch side of the door to pull it open.
Thanks,
Work is limited to two public use toilet rooms - changing floor and wall tile, changing plaster ceiling to gyp board, replacing toilet partitions and plumbing fixtures, changing light fixtures, changing HVAC grilles, and adjusting electrical switch height. There is no floor space reconfiguration except the possibility of shifting plumbing fixtures and partitions to meet IPC requirements.
Must ICC A117.1-2009 be followed in its entirety if not providing an accessible family or assisted-use toilet room (605.1.10)? The water closet compartments do not have the required floor spaces and without tearing down walls, they cannot be made compliant; also, compartment doors swing into the insufficient toilet clear floor spaces. If the door swing is reversed, then there will not be 18" clearance on the latch side of the door to pull it open.
Thanks,