Maybe, .....but....., if it is a 12' story, then it is at least 144' of ramp, plus 5' landings every 30' makes it about 200' of ramp....Price that out...
Example, using wildly exaggerated numbers for my market:
~13 yds of concrete at ~$120/yd = $1560
4 guys at 4 days = $4000 (and wouldn't they love it if they could really bill $250/day !)
Excavation/form rental/misc. = $2000
Total = $7560 - or $7.56/sf (average here for flat work is ~$4.00/sf)
You could double that number, and you're still not going to build an accessible elevator for that.