We do. Removed Fee schedule to shorten post.
Ordinance # 10-09-200
AN ORDINANCE REQUIRING THE PAYMENT OF PERMIT FEES BEFORE CONSTRUCTION OR UNDERTAKING HAZARDOUS OPERATIONS WITHIN THE CITY
WHEREAS, the Mayor and Board of Alderman of the have the obligation and authority pursuant to Sections 21-19-1 and 21-19-21 of Code of 1972, as amended, to enact all needful ordinances and codes necessary for the preservation of the public health, safety and welfare of the City; and
WHEREAS,the Mayor and Board of Alderman of , recognize the inherent dangers of hazardous operations and the need for plan review before the insulation of all fire preventive devices do hereby enact the following permit fee schedule in accordance with the International Fire Code Section 105.
Now, THEREFORE,be it ordained By the Mayor and Board of Alderman of the as follows:
Permit fees.
The following permits shall be issued and fees charged for the line items indicated with Section 2 penalties being assessed upon failure of the 3rd inspection. Fee schedule as follows:
Fire Prevention Bureau Permit and Fee Schedule
Operational Permit Fees as listed in the 2006 IFC Section 105
------------------------------------------------------------------------------------
The following operational permits are time sensitive or must be renewed
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
Construction Permit Fees as listed in the 2006 IFC Section 105.7
--------------------------------------------------------------------------------------------------------------------------------------------------------------
Alterations to or addition of the following shall be assessed as listed.
-----------------------------------------------------------------------------------
All systems included in a new project are included in the initial plan review and building permit fees if received with the initial (1st) plan set. If plans are not included in the 1st plan set the following fees apply in addition to building permit fees.
All plans must bear the wet stamp seal of a registered design professional in that field of expertise.
Section 2. PENALTY
1. A violation of any provision of this ordinance shall be punished by a fine not exceeding one thousand dollars ($1,000.00) or by imprisonment not to exceed ninety (90) days, or both. The minimum penalty for a first offense violation of this ordinance shall be one hundred dollars ($100.00). 2. Each day any violation of any provision of this ordinance shall continue shall constitute a separate offense.3. The penalties provided for in this Section shall be in addition to any other remedies available to the Governing Authority through the institution of an action or proceeding in any court, including but not limited to an action or proceeding to enjoin any violation of this ordinance.
Section 3. SEVERABILITYIf any section, subsection, sentence, clause, phrase or portion of this ordinance is for any reason held invalid or unconstitutional by any court of competent jurisdiction, such portion shall be deemed as a separate, distinct and independent provision, and such holding shall not affect the validity of the remaining portions thereof.Section 4. EFFECTIVE DATEThis ordinance shall become effective and be in full force from and after being certified by the City Clerk, signed by the Mayor or Board majority, recorded in the ordinance book, published and after waiting 30 days after the date of passage.
After first having been reduced to writing, then read and considered by the Mayor and Board of Aldermen, a motion was properly made by Alderman and duly seconded by Alderman , and a roll call vote was taken with the following results:
The foregoing ordinance was Ordained, Adopted and Approved by the Mayor and Board of Aldermen of the at a regular meeting thereof held on the 7th day of September, 2010. Witness my signature, the 7th day of September, 2010