jar546
CBO
Something did not look right at first glance on this LVL to LVL connection point.
Further looking revealed that this was an I-Joist hangar bent to fit and not the correct hangar for this application. This point was carrying 1/2 the load of 7 I-Joists for the 2nd floor.

Further looking revealed that this was an I-Joist hangar bent to fit and not the correct hangar for this application. This point was carrying 1/2 the load of 7 I-Joists for the 2nd floor.