Ryan Schultz
SAWHORSE
We are renovating an existing 1st floor space to a R2.
The floor assembly between this 1st floor R2 and the existing R2 on the 2nd floor, needs to be 2hr rated.
We have existing wood floor trusses with 3/4" CDX floor sheathing.
Is there anyway to get a 2hr rating floor assembly, by using just gyp bd and resilient channel below the trusses?
Basically looking to avoid having to pour a new layer of gyp crete on at the 2nd floor. Would have major cost implications.

The floor assembly between this 1st floor R2 and the existing R2 on the 2nd floor, needs to be 2hr rated.
We have existing wood floor trusses with 3/4" CDX floor sheathing.
Is there anyway to get a 2hr rating floor assembly, by using just gyp bd and resilient channel below the trusses?
Basically looking to avoid having to pour a new layer of gyp crete on at the 2nd floor. Would have major cost implications.